Project timelines (directional, from contract to opening)

Project type | Typical duration | Notes | Office tenant finish (TI) | 3–6 months | Plus design + permit time | Retail tenant finish | 2–5 months | Faster for vanilla-box conversions | Restaurant build

Project type Typical duration Notes
Office tenant finish (TI) 3–6 months Plus design + permit time
Retail tenant finish 2–5 months Faster for vanilla-box conversions
Restaurant build-out 4–7 months Kitchen MEP + health dept. add time
Medical / dental TI 4–8 months Imaging/specialty pushes longer
Ground-up retail / small commercial 8–14 months Includes sitework + shell + finish
Multifamily (garden / mid-rise) 8–18 months Scale and structure dependent
Industrial / warehouse (tilt-wall) 6–12 months Tilt-up is schedule-efficient

A useful framing for prospects: total time = design + permitting + construction. People underestimate design and permitting; a "9-month build" often means 12–15 months from "go" to "open" once design and permits are counted.

Ask Pereff AI about this topic

Pereff AI can go deeper — giving you project-specific ranges, comparing delivery methods, and answering follow-up questions instantly. Every answer is cited.

Ask: “Tell me more about Project timelines (directional, from contract to opening)

Want a project-specific take?

Articles give you the framework. Real numbers come from preconstruction — and Pereff charges nothing for that first conversation.

Start a Project